Office budget and spending
Every MP gets an annual budget to run their Ottawa and riding offices: staff, travel, mail-outs and contracts. It isn’t money for local projects.
Office budget for 2026–27, set by the House of Commons Board of Internal Economy
- Basic budget (same for every MP)$441,600
- Elector supplement (many voters)$38,910
- Geographic supplement (large area)$12,540
$89,922 spent in the first quarter of 2026–27, 18% of the year’s budget.
Spending reported by the office
| Quarter | Staff salaries | Travel | Hospitality | Contracts | Total |
|---|---|---|---|---|---|
| Apr–Jun 2025 | $41,786 | $10,552 | $0 | $16,440 | $68,778 |
| Jul–Sep 2025 | $75,644 | $12,147 | $1,575 | $17,544 | $106,910 |
| Oct–Dec 2025 | $59,609 | $12,446 | $11 | $20,250 | $92,315 |
| Jan–Mar 2026 | $69,397 | $11,884 | $150 | $16,701 | $98,132 |
| Apr–Jun 2026 | $58,251 | $13,530 | $156 | $17,984 | $89,922 |
| Since April 2025 | $304,688 | $60,559 | $1,891 | $88,919 | $456,056 |
April to June 2025 can include spending by the previous MP before the election on April 28, 2025. Constituency office rent and some central costs are paid from other budgets and aren’t shown here.
Federal projects in this riding
Infrastructure Canada projects in the towns and cities of Bruce—Grey—Owen Sound: transit, water, housing, recreation and more. Programs approve the funding, not individual MPs, so this shows what was funded here, not what one person delivered.
- Federal money
- $64.0M
- Completed
- 81
- Under construction
- 3
- Not started
- 1
Showing 40 of 85 projects, newest approval first
-
Albemarle Brook Restoration: Fresh water sustainability for Sky Lake, the Rankin River system and recreation at Sauble beachNot started$45,840federal, of $57.3K total cost
-
Gould Street and Pengally Avenue Watermain ReplacementUnder construction$1,060,550federal, of $2.7M total cost
-
Replacement of 7th Avenue Water TowerUnder construction$2,000,000federal, of $5.0M total cost
-
Replacement of Lakeshore Road and Algonquin Drive WatermainsUnder construction$729,278federal, of $1.8M total cost
-
Owen Sound Water Treatment Plant Filtration System ImprovementsCompleted$1,550,200federal, of $3.9M total cost
-
Rehabilitation of Municipal BuildingsCompleted$99,479federal, of $124.3K total cost
-
Bluewater Park Trail Enhancement ProjectCompleted$80,000federal, of $100.0K total cost
-
Waterfront Trail Remediation and RestorationCompleted$287,100federal, of $358.9K total cost
-
Rehabilitation of Bayfield Street Shoreline ProtectionCompleted$80,000federal, of $100.0K total cost
-
Backup Power Generator and Related InfrastructureCompleted$36,000federal, of $45.0K total cost
-
HVAC Air Conditioning and Ventilation UpgradeCompleted$362,321federal, of $452.9K total cost
-
Fixed Bottled Water Filling Station; External Wifi Access PointsCompleted$142,008federal, of $177.5K total cost
-
Trail Bridges Replacement | Hanover Community Trails SystemCompleted$860,640federal, of $2.2M total cost
-
Mary Street Water, Wastewater and Storm Sewer Replacement ProjectCompleted$1,099,008federal, of $2.7M total cost
-
Purchase 11 Specialized Transit Buses for Rolling StockCompleted$307,125federal, of $767.8K total cost
-
Replacement of Structure 043Completed$736,000federal, of $1.5M total cost
-
SMART Transit -Provide Scheduling Software and associated hardware to allow for efficient transportation schedulingCompleted$13,820federal, of $91.3K total cost
-
SMART Transit - Replace existing vehiclesCompleted$84,385federal, of $168.8K total cost
-
General Transit Terminal Repairs (signs)Completed$1,503federal, of $5.0K total cost
-
Waste Water Treatment Plant Standby Generator Design and ApprovalsCompleted$20,000federal, of $40.0K total cost
-
Purchase and installation of submersible mixer at Saugeen Composite Water towerCompleted$15,000federal, of $30.0K total cost
-
Purchase and installation of stand-by generator for the Saugeen Composite Water towerCompleted$53,557federal, of $119.0K total cost
-
Design and Construction of a new Biosolids storage facility to comply with Ministry of Environment and Climate Change guidelinesCompleted$267,790federal, of $1.3M total cost
-
Design Upgrades for Sewage Pump Station #1 located at 524 Taylor Street, WiartonCompleted$85,000federal, of $170.0K total cost
-
Gravity Sewer Inflow and Infiltration Investigation in Wiarton - work will occur throughout Wiarton, but will concentrate on Berford Street between Frank Street and Division StreetCompleted$78,690federal, of $157.4K total cost
-
Construction of Kenny Drain-Industrial Park Storm Water Management Pond and Diversion ChannelCompleted$880,000federal, of $1.8M total cost
-
Replace existing water standpipe with a larger volume standpipe to meet water pressures, fire flows, and foster economic growthCompleted$50,000federal, of $827.4K total cost
-
Ivan/Sykes/Paul Sewer Replacement and RestorationCompleted$250,000federal, of $500.0K total cost
-
Replacement of Existing Pumps at Wastewater Collection Pump Station #2 with Chopper PumpsCompleted$34,591federal, of $149.5K total cost
-
Rehabilitation and Replacement of Sanitary Collection System (Selected Sewer Mains and Maintenance Structures)Completed$173,183federal, of $356.6K total cost
-
Replacement of Exterior Walkway & Curbing at Transit TerminalCompleted$30,000federal, of $60.0K total cost
-
Roof Replacement at Transit TerminalCompleted$30,000federal, of $60.0K total cost
-
Heating, Ventilation and Air Conditioning (HVAC) - Replacement in Transit TerminalCompleted$6,033federal, of $30.0K total cost
-
Accessibility Upgrades in Transit TerminalCompleted$7,500federal, of $15.0K total cost
-
Installation of 20 new Bus Shelters with accessible signage and sidewalk connectorsCompleted$138,857federal, of $310.0K total cost
-
Purchase of 1 Accessible Transit VehicleCompleted$35,616federal, of $71.2K total cost
-
Water Treatment Plant UpgradeCompleted$500,000federal, of $1.5M total cost
-
Marine Emergency Duties Training and Research Centre at the Georgian College Owen Sound CampusCompleted$1,705,955federal, of $5.9M total cost
-
Grandview Drive & Susan Street Reconstruction / Development of Alternate Water Distribution Trunk MainCompleted$909,500federal, of $2.7M total cost
-
Upgrades to CP Trail 2014Completed$15,000federal, of $35.0K total cost
How to read this page
- The office budget pays for the MP’s staff and offices. Infrastructure money flows through federal programs, often with provinces and cities, and goes to the recipient listed on each project.
- Projects are matched to ridings by the town or city named in Infrastructure Canada’s records. A project in a city covering several ridings is counted as “shared” and left out of the totals unless you include it.
- Status comes from reported construction dates. Some projects finish before their dates are updated.