Every MP gets an annual budget to run their Ottawa and riding offices: staff, travel, mail-outs and contracts. It isn’t money for local projects.
Office budget for 2026–27, set by the House of Commons Board of Internal Economy
- Basic budget (same for every MP)$441,600
- Elector supplement (many voters)$38,910
- Geographic supplement (large area)$32,260
$142,332 spent in the first quarter of 2026–27, 28% of the year’s budget.
Spending reported by the office
| Quarter | Staff salaries | Travel | Hospitality | Contracts | Total |
|---|---|---|---|---|---|
| Apr–Jun 2025 | $64,657 | $8,972 | $0 | $14,248 | $87,878 |
| Jul–Sep 2025 | $124,885 | $40,108 | $0 | $25,204 | $190,197 |
| Oct–Dec 2025 | $57,233 | $43,586 | $0 | $21,881 | $122,700 |
| Jan–Mar 2026 | $135,412 | $25,917 | $0 | $15,745 | $177,074 |
| Apr–Jun 2026 | $77,759 | $43,671 | $250 | $20,653 | $142,332 |
| Since April 2025 | $459,945 | $162,255 | $250 | $97,731 | $720,181 |
April to June 2025 can include spending by the previous MP before the election on April 28, 2025. Constituency office rent and some central costs are paid from other budgets and aren’t shown here.
Federal projects in this riding
Infrastructure Canada projects in the towns and cities of Kamloops—Shuswap—Central Rockies: transit, water, housing, recreation and more. Programs approve the funding, not individual MPs, so this shows what was funded here, not what one person delivered.
- Federal money
- $905.1M
- Completed
- 104
- Under construction
- 15
- Not started
- 4
Showing 40 of 123 projects, newest approval first
-
Purchases to support continued transit service for South Shuswap, British Columbia.Under construction$54,264federal, of $67.8K total cost
-
Purchase of a wheelchair accessible vehicle to continue transportation services provided by the Shuswap Association for Community Living in Salmon Arm, British Columbia.Completed$94,000federal, of $127.4K total cost
-
Tkemlúps te Secwepemc - CLC Stormwater Detention FacilityNot started$1,000,000federal, of $1.4M total cost
-
Whispering Pines / Clinton Indian Band Living Revetment Site 2BCompleted$1,000,000federal
-
ECC - SD 83 - Highland Park Elementary Ventilation ImprovementsCompleted$556,339federal, of $695.4K total cost
-
Salmon Arm - Shaw Centre Heat Recovery and Air Handling UpgradeUnder construction$152,654federal, of $423.1K total cost
-
Traditional Use and Archeological Assessments - West Bay ConnectorNot started$50,000federal, of $57.2K total cost
-
Environmental Assessments & Compensation Plan - West Bay ConnectorNot started$50,000federal, of $56.9K total cost
-
Site Survey, Terrain mapping, Engineering design, Alignment and Costing West Bay ConnectorNot started$50,000federal, of $102.7K total cost
-
Westsyde Road Multi-Use PathwayUnder construction$738,000federal
-
BC Housing - Shuswap Ilahee LodgeCompleted$178,048federal, of $222.6K total cost
-
Purchase of a vehicle for free on-demand, door-to-door transportation service in Electoral Area C of the Columbia Shuswap Regional District (British Columbia)Completed$72,234federal, of $90.3K total cost
-
TOWN OF GOLDEN: FLOOD RESILIENCE HIGHWAY 95, KICKING HORSE I & II BRIDGE projectUnder construction$28,769,154federal, of $57.5M total cost
-
Kamloops - Tranquille Sanitary Sewer Upgrade Phase 3Under construction$6,906,698federal, of $17.3M total cost
-
Sicamous Narrows AT Crossing Feasibility StudyCompleted$50,000federal
-
Town of Golden Integrated Sanitary Sewer System Upgrades for Collection and TreatmentCompleted$592,200federal, of $1.5M total cost
-
Enderby Outdoor PoolUnder construction$2,000,000federal, of $5.0M total cost
-
Columbia Shuswap - Loftus Lake Fen Universal TrailCompleted$31,500federal, of $155.0K total cost
-
Golden - Mount 7 Rec Plex Gym Floor RenewalCompleted$103,360federal, of $258.4K total cost
-
Columbia Shuswap - Eagle Bay Community ParkCompleted$191,947federal, of $479.9K total cost
-
Columbia Shuswap - Scotch Creek WaterCompleted$1,280,000federal, of $3.2M total cost
-
Revelstoke - Wastewater Treatment Facility UpgradeUnder construction$5,359,200federal, of $13.4M total cost
-
Kamloops - North-South Kamloops Bicycle CorridorCompleted$3,200,000federal, of $4.0M total cost
-
North Okanagan - Shuswap North Okanagan Rail Trail: Enderby-Splatsin SectionCompleted$367,249federal, of $459.1K total cost
-
Golden - 8th Avenue S Multi-Use PathCompleted$249,200federal, of $311.5K total cost
-
Village of Chase Community Building ImprovementsCompleted$197,529federal, of $246.9K total cost
-
Splatsin Community Building ImprovementsCompleted$1,476,391federal
-
Kicking Horse River and Hospital Creek Dike ImprovementsCompleted$1,182,160federal, of $1.5M total cost
-
Sicamous - Community Bio-Heat ProjectCompleted$264,281federal, of $689.1K total cost
-
Kamloops - Canada Games Aquatic Centre RehabilitationCompleted$1,370,328federal, of $3.4M total cost
-
Sicamous - Shuswap (Secwepemc) Healing CentreUnder construction$3,554,359federal, of $5.9M total cost
-
Skeetchestn Indian Band - Skeetchestn Learning Garden CentreCompleted$489,658federal, of $652.9K total cost
-
Chase - Wilson Park Footbridge ProjectCompleted$60,000federal, of $150.0K total cost
-
Highway 1 Selkirk Mountain Four-LaningUnder construction$31,515,980federal, of $99.3M total cost
-
Highway 93/95 Radium Intersection Improvements and Corridor UpgradesCompleted$17,971,615federal, of $39.7M total cost
-
Trans-Canada Highway 1: Ford Road to Tappen Valley RoadUnder construction$82,142,934federal, of $164.3M total cost
-
Trans-Canada Highway 1 Four-Laning - Jumping Creek to Jack MacDonald Snow ShedUnder construction$45,741,474federal, of $91.5M total cost
-
Trans-Canada Highway 1 - R.W. Bruhn Bridge & ApproachesUnder construction$91,082,772federal, of $182.2M total cost
-
Trans-Canada Highway 1 - Quartz CreekUnder construction$49,924,542federal, of $99.8M total cost
-
Shuswap River Water Main CrossingCompleted$329,700federal, of $659.4K total cost
How to read this page
- The office budget pays for the MP’s staff and offices. Infrastructure money flows through federal programs, often with provinces and cities, and goes to the recipient listed on each project.
- Projects are matched to ridings by the town or city named in Infrastructure Canada’s records. A project in a city covering several ridings is counted as “shared” and left out of the totals unless you include it.
- Status comes from reported construction dates. Some projects finish before their dates are updated.