Office budget and spending
Every MP gets an annual budget to run their Ottawa and riding offices: staff, travel, mail-outs and contracts. It isn’t money for local projects.
Office budget for 2026–27, set by the House of Commons Board of Internal Economy
- Basic budget (same for every MP)$441,600
- Elector supplement (many voters)$25,970
- Geographic supplement (large area)$12,540
$103,107 spent in the first quarter of 2026–27, 21% of the year’s budget.
Spending reported by the office
| Quarter | Staff salaries | Travel | Hospitality | Contracts | Total |
|---|---|---|---|---|---|
| Apr–Jun 2025 | $38,650 | $13,670 | $510 | $24,067 | $76,896 |
| Jul–Sep 2025 | $94,705 | $13,185 | $328 | $28,472 | $136,690 |
| Oct–Dec 2025 | $68,876 | $17,035 | $1,124 | $32,494 | $119,529 |
| Jan–Mar 2026 | $78,836 | $13,954 | $643 | $57,795 | $151,228 |
| Apr–Jun 2026 | $50,852 | $19,228 | $649 | $32,378 | $103,107 |
| Since April 2025 | $331,919 | $77,071 | $3,254 | $175,207 | $587,450 |
April to June 2025 can include spending by the previous MP before the election on April 28, 2025. Constituency office rent and some central costs are paid from other budgets and aren’t shown here.
Federal projects in this riding
Infrastructure Canada projects in the towns and cities of Mégantic—L’Érable—Lotbinière: transit, water, housing, recreation and more. Programs approve the funding, not individual MPs, so this shows what was funded here, not what one person delivered.
- Federal money
- $80.7M
- Completed
- 84
- Under construction
- 1
- Not started
- 1
Showing 40 of 86 projects, newest approval first
-
Wastewater Collection and Treatment in Saint-FortunatNot started$5,069,397federal, of $10.1M total cost
-
Retrofit and updrage the Promutuel RoomCompleted$718,500federal, of $2.1M total cost
-
Space reorganization - Universal accessibility: Hospital entrance and reception deskCompleted$320,000federal, of $400.0K total cost
-
Renovation and upgrading of the domestic water network including the water inletCompleted$160,000federal, of $200.0K total cost
-
Repair of generators and increase in the capacity of the emergency electrical networkCompleted$1,517,909federal, of $1.9M total cost
-
Upgrades to the roofCompleted$240,000federal, of $300.0K total cost
-
Renovation of the Paul-de-la-Sablionnière Sports CentreCompleted$1,186,274federal, of $3.6M total cost
-
Rehabilitation of sports fieldsCompleted$42,085federal, of $132.7K total cost
-
Construction of a Water Game - AudetCompleted$67,614federal, of $202.9K total cost
-
Water Systems UpgradesCompleted$81,918federal, of $204.8K total cost
-
Water Systems UpgradeUnder construction$675,474federal, of $1.7M total cost
-
Water Systems UpgradesCompleted$237,050federal, of $592.6K total cost
-
Water System UpgradesCompleted$390,370federal, of $975.9K total cost
-
Water Systems UpgradesCompleted$369,070federal, of $922.7K total cost
-
Water Systems UpgradesCompleted$1,993,163federal, of $5.0M total cost
-
Water Systems UpgradesCompleted$1,267,587federal, of $3.2M total cost
-
Water Systems UpgradesCompleted$418,608federal, of $1.0M total cost
-
Water Systems UpgradesCompleted$530,200federal, of $1.3M total cost
-
Water Systems UpgradesCompleted$934,934federal, of $2.3M total cost
-
Replacement of water pipesCompleted$1,779,898federal, of $4.4M total cost
-
Sanitary sewer extension - Highway 271 and des Entreprises AvenueCompleted$94,500federal, of $260.8K total cost
-
Construction of a permanent structure over the multifunctional ice rinkCompleted$191,263federal, of $573.8K total cost
-
Renovation of the Carrefour de L'ÉrableCompleted$201,896federal, of $605.7K total cost
-
Stabilization and development of the bank of the Bécancour RiverCompleted$59,338federal, of $178.0K total cost
-
Renewal of water pipesCompleted$1,866,113federal, of $3.7M total cost
-
Renewal of water pipesCompleted$578,233federal, of $1.2M total cost
-
Renewal of water pipesCompleted$721,319federal, of $1.4M total cost
-
Renewal of water pipesCompleted$996,279federal, of $2.0M total cost
-
Renewal of water pipesCompleted$279,337federal, of $659.5K total cost
-
Renewal of water pipesCompleted$688,559federal, of $1.4M total cost
-
Infrastructure work for the 2018 Quebec GamesCompleted$375,333federal, of $1.1M total cost
-
Replacement of the aeration pipes in the treatment plantCompleted$183,700federal, of $367.4K total cost
-
Upgrading of the Ostiguy Water Supply System (Lac Jolicoeur)Completed$265,512federal, of $549.1K total cost
-
Wastewater collection system rehabilitation in East BroughtonCompleted$582,850federal, of $1.7M total cost
-
Renovation of the Cultural HallCompleted$15,251federal, of $50.8K total cost
-
Program for the renewal of drinking water and wastewater pipes (PRECO)Completed$442,883federal, of $1.4M total cost
-
Upgrades to Thetford Mines water treatment and distribution systemCompleted$22,326,678federal, of $50.9M total cost
-
Road improvements in Val-Racine and Notre-Dame-des-BoisCompleted$1,384,162federal, of $3.5M total cost
-
Champoux Street (Route 263) UpgradesCompleted$589,159federal, of $2.9M total cost
-
Repairs to the St-Louis BuildingCompleted$183,640federal, of $550.9K total cost
How to read this page
- The office budget pays for the MP’s staff and offices. Infrastructure money flows through federal programs, often with provinces and cities, and goes to the recipient listed on each project.
- Projects are matched to ridings by the town or city named in Infrastructure Canada’s records. A project in a city covering several ridings is counted as “shared” and left out of the totals unless you include it.
- Status comes from reported construction dates. Some projects finish before their dates are updated.