Office budget and spending
Every MP gets an annual budget to run their Ottawa and riding offices: staff, travel, mail-outs and contracts. It isn’t money for local projects.
Office budget for 2026–27, set by the House of Commons Board of Internal Economy
- Basic budget (same for every MP)$441,600
- Geographic supplement (large area)$32,260
$92,126 spent in the first quarter of 2026–27, 19% of the year’s budget.
Spending reported by the office
| Quarter | Staff salaries | Travel | Hospitality | Contracts | Total |
|---|---|---|---|---|---|
| Apr–Jun 2025 | $42,104 | $26,353 | $88 | $26,865 | $95,410 |
| Jul–Sep 2025 | $71,778 | $22,225 | $211 | $51,703 | $145,917 |
| Oct–Dec 2025 | $71,778 | $14,266 | $513 | $38,580 | $125,138 |
| Jan–Mar 2026 | $102,593 | $42,867 | $1,275 | $49,785 | $196,520 |
| Apr–Jun 2026 | $57,459 | $15,583 | $305 | $18,779 | $92,126 |
| Since April 2025 | $345,714 | $121,294 | $2,392 | $185,712 | $655,112 |
April to June 2025 can include spending by the previous MP before the election on April 28, 2025. Constituency office rent and some central costs are paid from other budgets and aren’t shown here.
Federal projects in this riding
Infrastructure Canada projects in the towns and cities of Moose Jaw—Lake Centre—Lanigan: transit, water, housing, recreation and more. Programs approve the funding, not individual MPs, so this shows what was funded here, not what one person delivered.
- Federal money
- $94.8M
- Completed
- 126
- Under construction
- 12
- Not started
- 7
Showing 40 of 145 projects, newest approval first
-
City of Moose Jaw - Spring Creek Stormwater Management ProjectNot started$6,425,300federal, of $16.1M total cost
-
Town of Milestone Water Treatment Plant UpgradesNot started$1,032,820federal, of $2.6M total cost
-
Town of Regina Beach-Landfill Decommissioning ProjectNot started$618,725federal, of $1.5M total cost
-
Village of Craven Water Supply and Treatment UpgradesNot started$801,000federal, of $2.0M total cost
-
Village of Loreburn - Regional Lagoon ExpansionNot started$545,600federal, of $1.4M total cost
-
Town of Gravelbourg Water Tower Decommissioning and Watermain ReplacementUnder construction$1,406,279federal, of $3.5M total cost
-
Resort Village of Shields - Low Pressure Collection SystemUnder construction$2,355,200federal, of $5.9M total cost
-
Village of Glenside Water Plant UpgradeCompleted$46,000federal, of $115.0K total cost
-
Village of Kenaston Lagoon ExpansionNot started$396,170federal, of $990.4K total cost
-
Village of Semans - Reverse Osmosis Water Treatment PlantNot started$364,000federal, of $910.0K total cost
-
Town of Watrous - Lagoon Outfall UpgradesUnder construction$655,318federal, of $1.6M total cost
-
Town of Watrous - Lagoon Outfall UpgradesUnder construction$244,922federal, of $612.3K total cost
-
Town of Davidson - Water Tower RehabilitationCompleted$182,000federal, of $455.0K total cost
-
Town of Pense - Wastewater Infrastructure UpgradesCompleted$368,160federal, of $920.4K total cost
-
Village of Viscount Well Water Development ProjectUnder construction$100,560federal, of $251.4K total cost
-
Village of Wilcox Phase II ESA and Landfill DecommissioningUnder construction$354,840federal, of $887.1K total cost
-
Purchase of an accessible vehicle and supporting equipment to provide on-demand transportation service for residents in the Central Butte Area, SaskatchewanCompleted$78,400federal, of $99.7K total cost
-
Town of Mossbank - Park TrailsCompleted$60,000federal, of $150.0K total cost
-
South Shore TrailCompleted$150,000federal, of $250.0K total cost
-
Town of Lumsden James St South Pathways System, Lumsden, SaskatchewanCompleted$110,664federal, of $184.4K total cost
-
Danielson Provincial Park Sewage Lagoon UpgradeCompleted$365,000federal, of $730.0K total cost
-
Purchase of a hybrid vehicle and construction of a garage for on-demand service in Gravelbourg and rural southwest SaskatchewanCompleted$78,853federal, of $98.6K total cost
-
Pasqua First Nation - New Spray ParkUnder construction$514,766federal, of $686.4K total cost
-
Town of Milestone - Landfill DecommissioningCompleted$151,084federal, of $377.7K total cost
-
Town of Gravelbourg-Landfill DecommissioningUnder construction$495,328federal, of $1.2M total cost
-
Moose Jaw Trails & Pathways Master Plan, Province of SaskatchewanCompleted$45,000federal
-
Town of Strasbourg - Lions Park Revitalization ProjectCompleted$183,640federal, of $459.1K total cost
-
Last Mountain Regional Landfill - Cell 4 Closure Plan and Long Term Closure PlanCompleted$118,560federal, of $296.4K total cost
-
Village of Avonlea - Landfill Assessment and ClosureUnder construction$458,590federal, of $1.5M total cost
-
Waste Water Treatment Upgrade Rowans ravine Provincial ParkCompleted$325,000federal, of $650.0K total cost
-
Utopia Conservation & Development Area Authority - Rouleau Flats Flood Protection ProjectCompleted$2,399,642federal, of $6.0M total cost
-
Resort Village of Kannata Valley - Storm Water Drainage Infrastructure ImprovementCompleted$8,485federal, of $21.2K total cost
-
Resort Village of Thode - Community Centre UpgradeCompleted$258,328federal, of $645.8K total cost
-
Resort Village of Shields - Municipal Sport Court Amenity/Maintenance Building RetrofitCompleted$61,303federal, of $153.3K total cost
-
Kenaston Community Recreation Board - Kenaston Arena Ice Plant ReplacementCompleted$152,852federal, of $382.1K total cost
-
Town of Imperial - Imperial Arena UpgradeCompleted$350,914federal, of $877.3K total cost
-
Rooftop Solar Power Upgrade - 3 Municipal Buildings and LED Lighting UpgradesCompleted$414,151federal, of $1.0M total cost
-
Village of Craven Park and Community GardenCompleted$38,084federal, of $95.2K total cost
-
Village of Elbow Line 19 Multi-Purpose FacilityCompleted$2,600,000federal, of $6.5M total cost
-
Town of Nokomis Lagoon ExpansionCompleted$543,775federal, of $1.4M total cost
How to read this page
- The office budget pays for the MP’s staff and offices. Infrastructure money flows through federal programs, often with provinces and cities, and goes to the recipient listed on each project.
- Projects are matched to ridings by the town or city named in Infrastructure Canada’s records. A project in a city covering several ridings is counted as “shared” and left out of the totals unless you include it.
- Status comes from reported construction dates. Some projects finish before their dates are updated.