Office budget and spending
Every MP gets an annual budget to run their Ottawa and riding offices: staff, travel, mail-outs and contracts. It isn’t money for local projects.
Office budget for 2026–27, set by the House of Commons Board of Internal Economy
- Basic budget (same for every MP)$441,600
- Elector supplement (many voters)$38,910
- Geographic supplement (large area)$32,260
$120,932 spent in the first quarter of 2026–27, 24% of the year’s budget.
Spending reported by the office
| Quarter | Staff salaries | Travel | Hospitality | Contracts | Total |
|---|---|---|---|---|---|
| Apr–Jun 2025 | $40,360 | $14,014 | $325 | $19,257 | $73,955 |
| Jul–Sep 2025 | $83,295 | $17,556 | $917 | $34,305 | $136,072 |
| Oct–Dec 2025 | $89,991 | $13,931 | $436 | $27,618 | $131,976 |
| Jan–Mar 2026 | $120,932 | $12,111 | $761 | $41,078 | $174,882 |
| Apr–Jun 2026 | $80,413 | $11,420 | $836 | $28,263 | $120,932 |
| Since April 2025 | $414,991 | $69,032 | $3,274 | $150,520 | $637,817 |
April to June 2025 can include spending by the previous MP before the election on April 28, 2025. Constituency office rent and some central costs are paid from other budgets and aren’t shown here.
Federal projects in this riding
Infrastructure Canada projects in the towns and cities of Saint-Maurice—Champlain: transit, water, housing, recreation and more. Programs approve the funding, not individual MPs, so this shows what was funded here, not what one person delivered.
- Federal money
- $108.9M
- Completed
- 97
- Under construction
- 2
- Not started
- 2
Showing 40 of 101 projects, newest approval first
-
Carrefour d'innovation sociale (centre for social entrepreneurship)Under construction$1,890,400federal, of $2.4M total cost
-
Nanonetwork of Maison Eurêka, ressource dhébergement en dépendanceCompleted$640,041federal, of $813.3K total cost
-
Repair work of site and classroom doorsCompleted$269,857federal, of $337.3K total cost
-
Renovation of sanitary blocksCompleted$214,051federal, of $267.6K total cost
-
Interior renovationCompleted$445,624federal, of $557.0K total cost
-
Site renovation and interior worksCompleted$286,932federal, of $358.7K total cost
-
Site WorksCompleted$102,618federal, of $250.0K total cost
-
Site WorksCompleted$364,860federal, of $459.3K total cost
-
Exterior work on the building and interior renovationCompleted$782,950federal, of $978.7K total cost
-
Roofing renovation, decontamination and interior lightingCompleted$679,253federal, of $849.1K total cost
-
Interior finishing and electromechanical workCompleted$304,322federal, of $380.4K total cost
-
Exterior work on the building and interior renovationCompleted$397,533federal, of $496.9K total cost
-
Building envelope and interior electromechanical workCompleted$293,677federal, of $367.1K total cost
-
Roofing workCompleted$366,027federal, of $457.7K total cost
-
Development of play modules for childrenCompleted$25,967federal, of $77.9K total cost
-
Corridor repairCompleted$224,000federal, of $280.0K total cost
-
Corridor repairCompleted$258,909federal, of $360.0K total cost
-
Interior finish repairCompleted$80,000federal, of $100.0K total cost
-
Repair of interior finishesCompleted$264,000federal, of $330.0K total cost
-
Repair of the heating systemCompleted$56,000federal, of $70.0K total cost
-
Replacement of windows and partial repair of exterior facingsCompleted$509,480federal, of $636.9K total cost
-
Repair of interior finishesCompleted$227,492federal, of $330.0K total cost
-
Schoolyard repairsCompleted$46,400federal, of $58.0K total cost
-
Renovation of outdoor facilitiesCompleted$349,600federal, of $437.0K total cost
-
Repair of interior finishesCompleted$644,000federal, of $805.0K total cost
-
Repair of mechanical systemsCompleted$184,712federal, of $330.0K total cost
-
Repair of the exterior claddingCompleted$52,710federal, of $100.0K total cost
-
Parking lot repairs and work on classroomsCompleted$513,832federal, of $642.3K total cost
-
Interior and exterior repairsCompleted$664,817federal, of $831.0K total cost
-
Interior and exterior repairsCompleted$487,390federal, of $609.2K total cost
-
Replacing the water supplyCompleted$138,738federal, of $400.0K total cost
-
Replacement of natural gas boilersCompleted$229,436federal, of $400.0K total cost
-
Boiler room refurbishment & interior renovationsCompleted$653,771federal, of $817.2K total cost
-
Schoolyard repairs and various finishesCompleted$309,759federal, of $580.0K total cost
-
Renovation of premises and bathroomsCompleted$836,000federal, of $1.0M total cost
-
Repair of balconies and porchesCompleted$120,000federal, of $150.0K total cost
-
Repair of exterior siding and interior finishesCompleted$276,202federal, of $345.3K total cost
-
Repair of security systemsCompleted$342,222federal, of $480.0K total cost
-
Repair of the exterior claddingCompleted$288,000federal, of $360.0K total cost
-
Repair of exterior cladding and pavingCompleted$483,474federal, of $604.3K total cost
How to read this page
- The office budget pays for the MP’s staff and offices. Infrastructure money flows through federal programs, often with provinces and cities, and goes to the recipient listed on each project.
- Projects are matched to ridings by the town or city named in Infrastructure Canada’s records. A project in a city covering several ridings is counted as “shared” and left out of the totals unless you include it.
- Status comes from reported construction dates. Some projects finish before their dates are updated.