Every MP gets an annual budget to run their Ottawa and riding offices: staff, travel, mail-outs and contracts. It isn’t money for local projects.
$470,280
Office budget for 2026–27, set by the House of Commons Board of Internal Economy
Basic budget (same for every MP)$441,600
Geographic supplement (large area)$28,680
No spending reports were found for this MP yet. New MPs appear after their first full quarter.
Federal projects in this riding
Infrastructure Canada projects in the towns and cities of The Eastern Peninsulas: transit, water, housing, recreation and more. Programs approve the funding, not individual MPs, so this shows what was funded here, not what one person delivered.
Federal money
$128.3M
Completed
264
Under construction
4
Not started
25
Showing 40 of 293 projects, newest approval first
Water Main Replacement - Phase 3
Centreville-Wareham-Trinity. Other, Canada Housing Infrastructure Fund - Provinces & Territories. Approved July 20, 2026. Recipient: Centreville-Wareham-Trinity, Town of.
Not startedExpected to start May 2027
$431,551federal, of $863.1K total cost
Gambo - Lift Station #14 Retrofit
Gambo. Other, Canada Housing Infrastructure Fund - Provinces & Territories. Approved July 20, 2026. Recipient: Gambo, Town of.
Not startedExpected to start May 2027
$192,703federal, of $385.4K total cost
Notre Dame Street - Water & Sewer Upgrades
St. Lawrence. Other, Canada Housing Infrastructure Fund - Provinces & Territories. Approved December 15, 2025. Recipient: St. Lawrence, Town of.
Not startedExpected to start May 2026
$480,026federal, of $960.1K total cost
Lift Station Upgrades
Glovertown. Wastewater, Canada Housing Infrastructure Fund - Provinces & Territories. Approved December 15, 2025. Recipient: Glovertown, Town of.
Not startedExpected to start Jun 2027
$181,367federal, of $362.7K total cost
New Chlorine Booster Station & Water Tower Repairs
Hare Bay. Other, Canada Housing Infrastructure Fund - Provinces & Territories. Approved December 15, 2025. Recipient: Hare Bay, Town of.
Not startedExpected to start May 2027
$356,232federal, of $712.5K total cost
Hollett's Place Water & Sewer Upgrade
Lewin's Cove. Drinking Water, Canada Housing Infrastructure Fund - Provinces & Territories. Approved December 2, 2025. Recipient: Lewin's Cove, Town of.
Not startedExpected to start May 2026
$198,721federal, of $397.4K total cost
Water Treatment Plant Replacement
Lumsden. Drinking Water, Canada Housing Infrastructure Fund - Provinces & Territories. Approved December 2, 2025. Recipient: Lumsden, Town of.
Not startedExpected to start Jan 2027
$3,838,057federal, of $7.7M total cost
Bond Road W/S, Force Main, & Lift Station upgrades
Whitbourne. Wastewater, Canada Housing Infrastructure Fund - Provinces & Territories. Approved December 2, 2025. Recipient: Whitbourne.
Not startedExpected to start Apr 2027
$1,258,828federal, of $2.5M total cost
Water & Sewer System Upgrade for Tucker's Lane
Winterton. Wastewater, Canada Housing Infrastructure Fund - Provinces & Territories. Approved November 25, 2025. Recipient: Winterton, Town of.
Not startedExpected to start Apr 2027
$483,582federal, of $967.2K total cost
Outfall Replacement
Glovertown. Wastewater, Canada Housing Infrastructure Fund - Provinces & Territories. Approved November 25, 2025. Recipient: Glovertown, Town of.
Not startedExpected to start Jun 2027
$249,379federal, of $498.8K total cost
Lift Station Retrofit
Old Perlican. Wastewater, Canada Housing Infrastructure Fund - Provinces & Territories. Approved November 25, 2025. Recipient: Old Perlican, Town of.
Not startedExpected to start Apr 2027
$184,499federal, of $369.0K total cost
St. Gabriel's Hall Renovations
Marystown. Other, Green and Inclusive Community Buildings Program. Approved November 19, 2025. Recipient: St. Gabriel's Hall Inc..
Not startedExpected to start May 2025
$1,000,000federal, of $1.3M total cost
Old Days Pond Increased Access to Nature
Bonavista. Other, Natural Infrastructure Fund. Approved December 17, 2024. Recipient: Bonavista, Town of.
Not startedExpected to start May 2026
$200,000federal, of $250.0K total cost
Purchases to support transit service for Clarenville, Newfoundland and Labrador.
Clarenville. Public Transit, Permanent Public Transit Program. Approved April 18, 2024. Recipient: Clarenville, Town of.
CompletedFinished Sep 2025
$165,016federal, of $206.3K total cost
Southside Dam Upgrade and Chlorination System
St. Bride's. Drinking Water, Green Infrastructure Stream. Approved October 23, 2023. Recipient: St. Bride's, Town of.
CompletedFinished Jun 2026
$214,141federal, of $535.4K total cost
Lift Station 7 Retrofit
Gambo. Wastewater, Green Infrastructure Stream. Approved October 19, 2023. Recipient: Gambo, Town of.
Not startedExpected to start May 2026
$128,809federal, of $322.0K total cost
2023 Northwest Road Rehabilitation
Musgravetown. Highways and Roads, Rural & Northern Infrastructure Stream. Approved October 18, 2023. Recipient: Musgravetown.
CompletedFinished Jun 2025
$181,190federal, of $543.5K total cost
Paving Program - Blackburn Street
Grand Bank. Highways and Roads, Rural & Northern Infrastructure Stream. Approved October 18, 2023. Recipient: Grand Bank, Town of.
CompletedFinished Sep 2024
$29,289federal, of $87.9K total cost
Catalina Sea Wall
Trinity Bay North. Disaster Mitigation, Green Infrastructure Stream. Approved September 19, 2023. Recipient: Trinity Bay North, Town of.
CompletedFinished Jul 2025
$276,222federal, of $690.6K total cost
Shoreline Erosion Control - Location 1
Fortune. Disaster Mitigation, Green Infrastructure Stream. Approved September 19, 2023. Recipient: Fortune, Town of.
CompletedFinished Mar 2025
$425,552federal, of $1.1M total cost
Admirals Brook
Old Perlican. Disaster Mitigation, Green Infrastructure Stream. Approved September 19, 2023. Recipient: Old Perlican.
CompletedFinished Jul 2026
$196,563federal, of $491.4K total cost
Main Beach Armour Stone
Old Perlican. Disaster Mitigation, Green Infrastructure Stream. Approved September 19, 2023. Recipient: Old Perlican.
CompletedFinished Jun 2026
$90,520federal, of $226.3K total cost
Bisson Cove Armour Stone
Old Perlican. Disaster Mitigation, Green Infrastructure Stream. Approved September 19, 2023. Recipient: Old Perlican.
CompletedFinished Jun 2026
$89,462federal, of $223.7K total cost
Water System Upgrades
Lamaline. Drinking Water, Green Infrastructure Stream. Approved July 25, 2023. Recipient: Lamaline, Town of.
CompletedFinished Jan 2025
$83,286federal, of $208.2K total cost
Thompson Street Water and Storm Sewer Upgrades
Marystown. Drinking Water, Green Infrastructure Stream. Approved July 4, 2023. Recipient: Marystown, Town of.
CompletedFinished Aug 2024
$304,995federal, of $762.5K total cost
Glendon Brook Bridge Replacement (AP-MCW-23181)
Marystown. Highways and Roads, Rural & Northern Infrastructure Stream. Approved July 4, 2023. Recipient: Marystown, Town of.
CompletedFinished Jun 2025
$117,897federal, of $353.6K total cost
Bunker Hill Road Water and Sewer - Phase ll
Fortune. Drinking Water, Green Infrastructure Stream. Approved July 4, 2023. Recipient: Fortune, Town of.
CompletedFinished Oct 2026
$341,221federal, of $853.1K total cost
Septic System Installation
Old Perlican. Wastewater, Green Infrastructure Stream. Approved July 4, 2023. Recipient: Old Perlican.
Not startedExpected to start May 2026
$41,714federal, of $104.3K total cost
Water Intake Upgrading
St. Bernard's-Jacques Fontaine. Drinking Water, Green Infrastructure Stream. Approved July 4, 2023. Recipient: St. Bernard's-Jacques Fontaine.
CompletedFinished Jun 2025
$35,861federal, of $89.7K total cost
Septic Tank
Norman's Cove-Long Cove. Wastewater, Green Infrastructure Stream. Approved July 4, 2023. Recipient: Norman's Cove - Long Cove.
CompletedFinished Jan 2024
$160,414federal, of $401.0K total cost
Lift Station Retrofits
Bonavista. Wastewater, Green Infrastructure Stream. Approved July 4, 2023. Recipient: Bonavista, Town of.
CompletedFinished Dec 2025
$369,069federal, of $922.7K total cost
Water and Sewer Upgrading - Shaheen Crescent - Phase 2
Come By Chance. Wastewater, Green Infrastructure Stream. Approved July 4, 2023. Recipient: Come by Chance, Town of.
CompletedFinished Nov 2025
$360,920federal, of $902.3K total cost
Water & Sewer Upgrades - Phase I
Indian Bay. Drinking Water, Green Infrastructure Stream. Approved June 14, 2023. Recipient: Indian Bay, Town of.
Marystown. Drinking Water, Green Infrastructure Stream. Approved June 14, 2023. Recipient: Marystown, Town of.
CompletedFinished Jul 2026
$174,381federal, of $436.0K total cost
Barbour Avenue Water Main Extension
Sandy Cove. Drinking Water, Green Infrastructure Stream. Approved June 14, 2023. Recipient: Sandy Cove, Town of.
CompletedFinished Jun 2025
$193,341federal, of $483.4K total cost
Augustus Drive Booster Pump
Burin. Drinking Water, Green Infrastructure Stream. Approved June 14, 2023. Recipient: Burin, Town of.
CompletedFinished Jan 2025
$107,701federal, of $269.3K total cost
Bell Pond Water Systems
Old Perlican. Capacity Building, Green Infrastructure Stream. Approved June 14, 2023. Recipient: Old Perlican.
Not startedExpected to start May 2026
$72,547federal, of $181.4K total cost
Point May Community Center Retrofit
Point May. Recreation, Community, Culture & Recreation Infrastructure Stream. Approved June 14, 2023. Recipient: Point May, Municipality of.
CompletedFinished Nov 2024
$20,910federal, of $62.7K total cost
Water and Sewer Services Phase 4
Carmanville. Drinking Water, Green Infrastructure Stream. Approved June 6, 2023. Recipient: Carmanville, Town of.
Not startedExpected to start May 2026
$439,383federal, of $1.1M total cost
Waterline Replacement Phase 4
Long Harbour-Mount Arlington Heights. Drinking Water, Green Infrastructure Stream. Approved June 6, 2023. Recipient: Long Harbour-Mount Arlington Heights, Town of.
CompletedFinished Jul 2024
$237,443federal, of $593.6K total cost
How to read this page
The office budget pays for the MP’s staff and offices. Infrastructure money flows through federal programs, often with provinces and cities, and goes to the recipient listed on each project.
Projects are matched to ridings by the town or city named in Infrastructure Canada’s records. A project in a city covering several ridings is counted as “shared” and left out of the totals unless you include it.
Status comes from reported construction dates. Some projects finish before their dates are updated.